By Fanuel Chinowaita

THE Zimbabwe Energy Regulatory Authority (ZERA) has introduced a raft of new regulations targeting electricity generation, solar installations, energy efficiency, electric vehicle charging stations and electricity infrastructure, in a move aimed at strengthening consumer protection, improving safety and promoting efficiency in the energy sector.
The regulations were unpacked during a two-day Electricity and Energy Management Awareness Workshop held at Holiday Inn Hotel in Mutare on November 19 and 20, 2026, which brought together electricians, engineers, energy sector players and other stakeholders.
The workshop, which combined electricity regulations awareness with energy management training, also sought to improve compliance with technical standards and promote responsible energy consumption.
Speaking during the engagement, ZERA Engineer Keith Chikomo said the newly promulgated regulations were intended to improve service delivery while strengthening the relationship between the regulator and energy sector stakeholders.
“It is always a pleasure for me to engage with several of our stakeholders and today, more particularly, with our valued stakeholders in the energy sector, as we talk about recently promulgated regulations that are earmarked to improve service delivery,” said Chikomo.
He said the engagement was particularly important for electricians, who were expected to benefit from discussions on ZWS 400, the Zimbabwe Standard for electrical wiring.
“As we talk about recently promulgated regulations, it is my pleasure to welcome you all to this Electricity and Energy Management Regulations, ZWS 400, which is our standard for wiring. I have noted a lot of electricians here, so this standard is going to be very helpful and energy efficient,” he said.
Chikomo said ZERA remained committed to consumer protection, energy sustainability and improving access to reliable energy services.
He added that consumers experiencing challenges with licensed energy service providers had an avenue to seek assistance from the regulator.
“Should you have any issue against a licensee or a service provider within the energy sector, you have got an avenue to approach the regulator for redress. So it is something that is available and something that we do as ZERA,” he said.
Among the regulations discussed was Statutory Instrument 187 of 2026, the Energy Regulatory (Solar Products and Installation) Regulations, which introduce requirements for solar product suppliers, importers, manufacturers and installers.
The regulations require manufacturers and importers intending to sell solar products in Zimbabwe to register their products with ZERA, providing relevant product details, warranty information and test reports demonstrating compliance with applicable standards.
The authority is also required to maintain and publish a register of approved solar products and consumer devices.
Solar installers will also be required to obtain licences from ZERA, while installations must comply with prescribed safety standards, including separate earthing systems for direct current (DC) and alternating current (AC) components.
Upon completing installation works, installers are required to issue completion certificates to clients and notify the electricity distribution licensee and ZERA.
The regulations further provide for minimum product warranties, inspections of premises dealing in solar equipment, seizure of non-compliant products and consumer compensation.
Disputes between consumers and solar suppliers or installers can also be referred to ZERA for resolution.
The solar regulations are scheduled to come into force six months after their publication in the Government Gazette on July 31, 2026.
Electricity generation and licensing reforms
ZERA Chief Engineer for Electricity Victor Sibanda led technical presentations outlining changes to the licensing framework and requirements governing electricity generation projects.
Under the Electricity (Licensing) (Amendment) Regulations, 2026, Statutory Instrument 125 of 2026, commercial electricity generation projects with a capacity of up to 10 megawatts are exempted from licence fees, while revised charges apply to projects exceeding that threshold.
The framework also provides exemptions for electricity generation facilities established for own consumption and non-commercial off-grid generation.
Meanwhile, SI 126 of 2026, which deals with licensing capacity for own-consumption electricity generation undertakings, requires facilities with capacities ranging from 100 kilowatts to 10 megawatts to be registered with ZERA before construction.
Projects exceeding 10 megawatts require a licence from the authority.
Applicants are required to submit supporting documentation, including grid impact assessment reports, company registration documents, proof of access to land and environmental impact assessment certificates or exemption letters from the Environmental Management Agency.
Another significant development is the introduction of virtual net metering through SI 127 of 2026, which amends the existing Electricity (Net Metering) Regulations.
The amendment allows electricity credits generated from renewable energy sources at one point of supply, or a group of supplies, to be transferred to another point of supply, including facilities located in different geographical areas.
Applications must be submitted to the distribution licensee, accompanied by proof of ownership or lease of facilities, agreements demonstrating a commercial relationship and a net metering certificate.
The distribution licensee is required to determine applications within 21 days, either approving or rejecting them with reasons.
The regulations also provide for payment to participants for cumulative excess electricity exported to the grid at the end of the annual billing cycle, subject to applicable taxes and levies.
The workshop further addressed SI 128 of 2026, which regulates the provision of electricity backbone infrastructure in new property developments.
Under the regulations, developers are responsible for providing electricity infrastructure, including distribution lines, transformers, mini-substations and service connection points.
The costs of constructing the infrastructure are to be borne entirely by developers and cannot be recovered from the electricity utility.
Developers must also obtain approval from the primary distribution licensee before commencing electrical infrastructure works.
The regulations prohibit the sale, leasing or disposal of stands within a development before the developer demonstrates compliance with the prescribed requirements.
Completed infrastructure must undergo inspection and certification before ownership is transferred to the primary distribution licensee, which assumes responsibility for its operation and maintenance. Developers are also required to provide a five-year warranty.
Energy efficiency and management
The workshop also examined SI 119 of 2026, the Electricity (Minimum Energy Performance Standards for Appliances and Labelling) Regulations, and SI 122 of 2026, the Electricity (Energy Management) Regulations.
The appliance regulations seek to address the importation and sale of inefficient electrical appliances by requiring manufacturers and importers to comply with prescribed minimum energy performance standards.
Regulated appliances must carry energy-performance labels displaying either star-based ratings or an A-to-G classification, which must be visible on the appliances and their packaging.
Manufacturers and importers are also required to obtain conformity certification from accredited testing facilities, while non-compliant appliances may be seized and disposed of in accordance with the regulations.
Under SI 122 of 2026, facilities with an installed capacity of at least 100kVA or classified as maximum-demand customers are designated for energy management purposes.
The regulations provide for mandatory energy audits, energy-performance ratings, minimum energy performance standards for industrial equipment, licensing of energy management professionals and registration of Energy Service Companies.
Designated facilities are also required to develop energy management policies aligned with ZWS ISO 50001 and submit them to ZERA for approval.
Existing designated facilities have 12 months from the promulgation of the regulations to submit their policies, while new facilities must do so before being connected to electricity supply.
The November 20 training session also focused on helping technical personnel translate energy data, engineering assessments and recommendations into practical decisions that deliver measurable savings.
Participants were encouraged to use reliable measurements, identify causes of abnormal energy consumption, quantify financial and operational implications and recommend practical interventions.
New standards for electrical installations
The Standards Association of Zimbabwe (SAZ) also presented on its role in developing and promoting national standards, including those governing electrical installations and energy management.
Among the standards discussed was ZWS 400:2024, the Code of Practice for Electrical Wiring of Premises, which provides requirements for the design, selection, installation, inspection and testing of electrical installations.
The standard covers cables and conductors, wiring methods, earthing, protection against electrical shocks, circuit loading, switchboards, distribution boards, fuses, electrical accessories and lighting fittings.
SAZ explained that the requirements were intended to ensure electrical installations and components were correctly selected, adequately protected, properly installed and safe for users.
The association also presented ZWS ISO 50001, which provides a framework for organisations to establish, implement and continually improve energy management systems.
The standard encourages organisations to identify major energy-consuming operations, establish energy performance indicators, set measurable targets and monitor improvements in energy consumption.
SAZ emphasised that it is Zimbabwe’s national standards body, responsible for developing and promoting standards, providing testing, calibration, certification, inspection and training services.
However, it clarified that it is not a regulator and does not independently legislate or enforce standards.
Regulatory authorities determine when standards become mandatory by adopting or referencing them in legal instruments.
Participants were also informed that standards referenced in ZERA Statutory Instruments 118 to 129 of 2026 were being offered at a 50 percent discount until the end of November 2026.
Expanding access and protecting consumers
Chikomo further highlighted energy security, universal access and consumer protection as key priorities for the regulator.
He said ZERA was working towards expanding energy access, particularly in rural communities, through initiatives such as the promotion of containerised service stations.
The initiative is intended to improve access to energy services in underserved areas.
On fuel quality, he said the authority conducted inspections and testing at service stations to ensure petroleum products met established specifications and standards.
The Mutare workshop formed part of ZERA’s broader stakeholder awareness programme aimed at familiarising energy sector players with the new regulatory framework and promoting safer, more efficient and sustainable energy practices.